BusinessAbani Sahu25 Nov 2026
New Delhi, Nov 25: The Union Cabinet has approved a ₹4,288.26-crore project to develop a second container terminal at Kamarajar Port Limited (KPL) in Tamil Nadu, a move aimed at expanding cargo-handling capacity and strengthening India’s maritime trade links.
Representational Image
The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, cleared the project under the Public Private Partnership (PPP) model on a Design, Build, Finance, Operate and Transfer (DBFOT) basis.
The proposed terminal will have a 900-metre-long berth, a design draft of 18 metres and the capacity to handle 2 million twenty-foot equivalent units (TEUs) annually. The development will take place in two phases, with the first phase providing 1.1 million TEUs of capacity and the second adding another 0.9 million TEUs.
The estimated PPP project cost, inclusive of GST, stands at ₹4,288.26 crore. Of this, ₹2,429.32 crore has been earmarked for Phase I and ₹1,858.94 crore for Phase II. The selected private concessionaire will arrange the investment. Kamarajar Port will separately bear an estimated dredging cost of ₹450 crore.
A key feature of the new terminal will be its ability to accommodate some of the world's largest container vessels, including ships measuring up to 400 metres in length and carrying up to 24,346 TEUs.
The 18-metre design draft is expected to improve the port's capacity to receive large mainline vessels and strengthen its connections with international shipping routes. This could also help reduce reliance on overseas deep-water transshipment hubs and the additional feedering costs associated with them.
The project is intended to cater to rising export-import cargo demand from the Chennai–Ennore industrial belt and the wider southern hinterland. Automobile and auto-component manufacturers, engineering units, electronics producers, chemical industries and other manufacturing sectors are among the key potential users of the expanded facility.
The expansion comes as container traffic at Kamarajar Port continues to grow. During FY 2025–26, the port handled 49.08 million tonnes of cargo and 1,008 vessels, including more than 7 lakh TEUs of container traffic.
Its existing container terminal has an installed annual capacity of 0.8 million TEUs and handled around 0.7 million TEUs during the financial year, translating into utilisation of approximately 88%.
Container traffic across India has grown at an estimated compound annual growth rate (CAGR) of 7% over the past five years. Kamarajar Port recorded a faster growth rate of around 9.9% in container traffic during the same period. The projected increase in regional demand has strengthened the case for additional capacity.
The project will be awarded through an open global competitive bidding process and implemented over a 40-year concession period, including a 48-month construction phase.
Under the proposed schedule, Phase I is to be completed within 24 months of the award of concession, with commercial operations expected to begin in the 25th month. Construction of Phase II will run from the 25th to the 48th month, followed by full commercial operations in the 49th month.
The concessionaire will recover its investment through user charges in accordance with the concession agreement and the applicable tariff framework. The project proposal also calls for environmental and other required clearances to be secured within a defined timeline before the bid due date.
The additional terminal capacity is expected to provide a stronger maritime gateway for export-import cargo originating from industrial clusters in Tamil Nadu and neighbouring states. It is also expected to improve logistics efficiency, support manufacturing activity and strengthen the competitiveness of India's eastern coastline in international trade.
The project is likely to generate employment for around 750 people directly and indirectly during construction. The operational phase is expected to create opportunities for approximately 800 people.
Industries across Tamil Nadu, Karnataka, Andhra Pradesh, Telangana and adjoining regions are expected to benefit from improved port infrastructure and logistics support. The development is also aligned with the objectives of Atmanirbhar Bharat, Maritime India Vision 2030 and Maritime Amrit Kaal Vision 2047.
The Centre has stated that there will be no financial implication for the Government of India towards the PPP component, as the selected concessionaire will arrange the required investment.
Formerly known as Ennore Port Limited, Kamarajar Port is one of India's 12 major ports and is wholly owned by the Chennai Port Authority under the Ministry of Ports, Shipping and Waterways.
Located on Tamil Nadu's east coast near the Chennai industrial and economic region, the port handles a diverse range of cargo, including coal, petroleum products, LNG, LPG, automobiles, containers and general cargo.
In FY 2025–26, KPL recorded revenue of approximately ₹1,280 crore and a profit before tax of ₹924 crore. Its overall cargo traffic registered a CAGR of 13.64% over the preceding five years.
The second container terminal is expected to reinforce the port's role in serving the manufacturing and trade hubs of southern India while adding capacity to the country's maritime logistics network.